Hamilton Wanted $6.7 Million for East Colonial Highway. NVTA Sent $1.6 Million.

A Hamilton parent who has lived on S. James Street since 2014 wrote to the Northern Virginia Transportation Authority this spring with a simple complaint: her four kids cannot get from their neighborhood to the rest of town without crossing East Colonial Highway, and there is no crosswalk or sidewalk on the south side of the road near the Post Office to help them do it. She was one of several residents who submitted comments this year backing the town's request for regional transportation dollars, a request Hamilton has been building toward since at least 2023.

On July 9, 2026, NVTA adopted its FY2026-2031 Six Year Program, a $776 million package funding 21 projects across eight Northern Virginia jurisdictions. Loudoun County walked away with two awards: $200 million for the Route 50 North Collector Road, and $1.6 million for Colonial Highway pedestrian safety improvements, the same East Colonial Highway project Hamilton had been asking the town's residents to write letters about since April 2026.

The town's actual funding request was $6.7 million. What arrived is less than a quarter of that.

What the Money Was Supposed to Cover

The scope Hamilton pitched to NVTA was not vague. The project description on file calls for new sidewalks and pedestrian crossings on both sides of East Colonial Highway, new curb and gutter to fix drainage problems along the corridor, and sidewalk lighting. That matches the conceptual plan Kimley-Horn engineers Mark Phillips and Hunter Streb presented to the Hamilton Town Council back in July 2024, built from ideas residents raised at a design charrette the previous August. That plan added buffers and lane narrowing to slow traffic, plus driveway entrance improvements to give the corridor some visual continuity. Zoning Administrator Martha Mason Semmes summed up the design brief at the time: residents wanted to keep it simple.

Kimley-Horn's preliminary estimate for that full build was $6.5 to $7 million, which is almost exactly the $6.7 million figure the town formally requested from NVTA when it applied in 2026. Town Project Planner Earl Dubin told the council in 2024 that missing a grant funding window could push the whole project back by two years, and pointed to SMARTSCALE, VDOT revenue sharing, and Federal Highway Administration grants as backup paths if NVTA came up short.

NVTA came up short. Not because Hamilton's case was weak, but because the math around this program is unforgiving almost everywhere. The authority received 27 applications this cycle requesting a combined $1.265 billion and had $776 million to give out. Every project on the list took a haircut relative to what its jurisdiction wanted, and small pedestrian corridors compete for the same pool as regional roadway megaprojects. NVTA's funding rules require the authority to prioritize projects by congestion reduction per dollar spent, a scoring method that in past funding cycles has left roadway widenings and interchange projects better funded than sidewalk and crosswalk work.

What $1.6 Million Looks Like Next to Everyone Else's Award

Sitting the Hamilton number next to other projects funded in the same round shows how far $1.6 million stretches on a corridor that was priced at $6.5 to $7 million to build in full.

Project

Jurisdiction

Amount Awarded

Colonial Highway pedestrian safety

Hamilton (Loudoun County)

$1.6 million

South Elden Street corridor improvements

Town of Herndon

$4.4 million

Annandale Road multimodal improvements

City of Falls Church

$30 million

Route 50 North Collector Road

Loudoun County

$200 million

Herndon's South Elden Street award, at nearly triple Hamilton's, is closer to what a fully realized sidewalk and crosswalk corridor can look like when NVTA funds it in one pass. Hamilton's $1.6 million sits at a scale more consistent with design, engineering, and a first phase of construction than with the buffers, lane narrowing, and continuous sidewalks on both sides of the road that the 2024 concept called for.

The Gap the Money Doesn't Close

The S. James Street resident who wrote to NVTA in support of the project was clear-eyed about its limits even before anyone knew the award amount. She noted the plan as designed does not reach her neighborhood's specific crossing near the Post Office, though she still supported it because of what it would do for pedestrian safety elsewhere along the corridor. Another commenter, who grew up in Hamilton, pointed to the same root problem: a wide road built for speed running straight through a residential town, with no consistent sidewalk network to counter it.

East Colonial Highway is not a side street Hamilton could route around this problem. Route 7 Business is the only primary highway that directly serves the town, which is why the corridor carries both through-traffic and every resident walking to the Hamilton Safety Center at the intersection with Hamilton Station Road, to the Post Office, or toward the businesses that line downtown. In a town of roughly 600 people packed into a fifth of a square mile, there is no alternate route to design around.

A $1.6 million award funds real engineering and likely a first phase of physical work. It does not fund the full corridor treatment residents asked for at that 2023 charrette, and it does not resolve the specific gap the S. James Street family flagged. Dubin's 2024 warning about missing funding windows and losing two years suggests the town already understood this project would likely come in phases rather than as one completed corridor. This award appears to confirm that read.

What Happens From Here

The town's own history with this project points to what comes next. After the 2024 council vote, which passed 6-0-1 to pursue outside funding with Dubin, Semmes, and Mayor Ken Wine leading the applications, Hamilton pursued multiple tracks at once rather than waiting on a single source. NVTA was one option among several, alongside SMARTSCALE, VDOT revenue sharing, and Federal Highway Administration grants. With $1.6 million now in hand for design and an initial phase, the remaining $5 million or so of the original estimate will likely have to come from one or more of those other channels, on their own separate timelines.

For anyone who walks East Colonial Highway on a normal week, whether to the Safety Center, the Post Office, or downtown, this is not a signal that new sidewalks are landing this year. It is a signal that a project residents have been pushing since 2023 has finally cleared its first real funding hurdle, and that the town now has money in hand to move design work forward rather than staying in the position of asking for a full $6.7 million all at once. The next visible milestone to watch for is how Hamilton scopes what this first phase actually builds, and whether the town returns to NVTA, SMARTSCALE, or VDOT for the balance.

If you want the fuller backstory on what makes daily life in Hamilton distinct, from its Quaker-era Main Street to the wineries just outside town, our Hamilton neighborhood guide covers the parts of town this project runs through.

Questions about how infrastructure projects like this one tend to affect property values or timing in Western Loudoun towns? Diana Geremia has been working this market since 1998 and can walk you through what's actually changing on the ground. Let's Connect.

Follow Me On Social Media

Work With Diana

As a lifelong resident of Western Loudoun County and the Washington, D.C. metropolitan area, I bring unparalleled local expertise to every transaction. With 19 years of experience and hundreds of successful home sales, I have the knowledge, negotiation skills, and market insight to help you achieve the best possible outcome.

Follow Me on Instagram